Arrange the steps in CPM
(A). Activity Sequence Establishment
(B). Activity Specification
(C). Critical Path Diagram for Project Progress
(D). Identification of the Critical Path
1
A, B, C, D
2
B, A, D, C
3
C, D, B, A
4
D, A, B, C