Teaching UGC NET Mock Test Series 2025 (Paper 1 & 2) Construction Materials and Management Project Planning PERT
Statement (I): The critical path has been defined as the longest duration path between the first and the last nodes of a project.
Statement (II): The duration of a project is not always the same as the duration of its critical path.
Statement (III): The Earliest start and finish times of an activity are based on the condition that every activity will not be started and finished as early as possible.
Find the correct code for given statements being correct or incorrect.
1
Statement (I) and (II) are correct but (III) is not correct.
2
Statement (I) and (III) are correct but (II) is not correct.
3
Statement (I) is correct but (II) and (III) are not correct.
4
Statement (II) is correct but (I) and (III) are not correct.