Which of the following are the primary objectives of risk monitoring in software project tracking?

P: To assess whether predicted risks do, in fact, occur
Q: To ensure that risk aversion steps defined for the risk are being properly applied
R: To collect information that can be used for future risk analysis

1
Only P and Q
2
Only P and R
3
Only Q and R
4
All the P, Q, R