An _______ chart is a project schedule representation that presents project plan as directed graph. The critical path is the _______ sequence of _______ tasks and it defines project ______

1
Activity, Shortest, Independent, Cost
2
Activity, Longest, Dependent, Duration
3
Activity, Longest, Independent, Duration
4
Activity, Shortest, Dependent, Duration