Assume the following regarding the development of a software system P:

- Estimated lines of code of P: 33, 480 LOC

- Average productivity for P: 620 LOC per person-month

- Number of software developers: 6

- Average salary of a software developer: ` 50,000 per month

If E, D and C are the estimated development effort (in person-months), estimated development

time (in months), and estimated development cost (in ` Lac) respectively, then (E, D, C) = 

1
(48, 8, 24)
2
(54, 9, 27)
3
(60, 10, 30)
4
(42, 7, 21)