Which of the following is used to determine the cost performance index? 

1
Budgeted cost of work performed - budget at completion
2
Budgeted cost of work performed ÷ budget at completion
3
Budgeted cost of work performed ÷ Actual cost of work performed
4
Budgeted cost of work performed - Actual cost of work performed