Arrange the steps involved in preparation of PERT / CPM in proper sequence.

A. Network construction

B. Time estimates of activities 

C. Sequential arrangement of activities

D. Critical activities are determined

E. Identification of activities

Choose the correct answer from the options given below: 

1
A, C, B, D, E
2
E, C, B, A, D
3
E, B, D, A, C
4
A, E, B, C, D