Match List - I with List - II.
|
List I (System) |
List II (Usage) |
||
|
A. |
PERT |
I. |
used for the physical and logical descriptions of system |
|
B. |
DFD |
II. |
generally two pairs of time/ cost estimates a normal cost/ time schedule and a crash cost/time schedule |
|
C. |
CPM |
III. |
Event, Activity, Dummy activity, Merge event |
|
D. |
LIbQual |
IV. |
based on users evaluation |
Choose the correct answer from the options given below :
1
A - III, B - IV, C - I, D - II
2
A - II, B - III, C - IV, D - I
3
A - I, B - II, C - III, D - IV
4
A - III, B - I, C - II, D - IV