XYZ Ltd. funrnished you with the following information:

  Budget Actual (in a particular month)
No. of working days 25 27
Production (in units) 20,000 22,000
Fixed overhead (in Rupees) 30,000 31,000

Budgeted overhead rate is Rs. 1 per unit. In a particular month the actual hours worked were 31,500.

What is the total overhead variance in the given month experienced by the XYZ Ltd?

1
Rs. 4,000 (Favourable)
2
Rs. 2,000 (Adverse)
3
Rs. 1,000 (Adverse)
4
Rs. 2,000 (Favourable)