Teaching UGC NET Mock Test Series 2025 (Paper 1 & 2) Industrial Engineering Operations Research PERT and CPM
Sequence correctly the following steps in PERT/CPM analysis:
(A) Identify the critical path
(B) Draw the network diagram
(C) Establish dependencies across activities
(D) Estimate the completion time of an activity
(E) Define the activities in the network
1
(B), (C), (D), (E), (A)
2
(E), (C), (B), (D), (A)
3
(C), (B), (E), (A), (D)
4
(A), (B), (D), (E), (C)