Arrange the phases of capital expenditure / Investment planning and control from beginning to end.
A. Evaluation of the net benefits
B. Identification of Investment opportunities.
C. Development of forecasts of benefits and costs.
D. Authorization for progressing and spending capital expenditure.
E. Control of capital Projects.
Choose the correct answer from the options given below:
1
A, C, D, E, B
2
B, C, A, D, E
3
A, B, C, D, E
4
B, A, D, C, E