Arrange the following steps of Activity Based Costing (ABC) in proper sequence -
A. Staff Training and Review Follow up
B. Identify Main Activities
C. Process specification
D. Identify Non-value adding Activity and cost pools
E. Selection of Activity Cost Drivers and Tracing of Costs with objects
Choose the correct answer from the options given below:
1
C, B, D, E, A
2
B, C, D, E, A
3
D, B, C, A, E
4
E, D, B, C, A