Arrange the steps of PERT/CPM in chronological order.
A. Determine the earliest and latest feasible event times
B. Identify the precedence relationships among the activities
C. Identify activities required by the project
D. Determine the expected time requirement for each activity
E. Develop a network diagram of activities and events or nodes showing precedence relationships
1
E, B, D, A, C
2
C, B, D, E, A
3
B, C, E, D, A
4
D, A, E, B, C