Comprehension Passage
Consider the process listed below;
|
Process |
Arrival Time |
Service Time |
|
P1 |
0.000 |
3 |
|
P2 |
1.001 |
6 |
|
P3 |
4.001 |
4 |
|
P4 |
6.001 |
2 |
What is the average turnaround time using Shortest Job first (non-pre-emptive)?
1
6.75
2
7.25
3
6.25
4
None of these