Which of the following statement is NOT correct about PERT ?
1
PERT was developed primarily to simplify the planning and scheduling of large and complex projects.
2
In a PERT chart, ‘Nodes’ represent the activities or tasks and ‘Arrows’ represent events or milestones in the project.
3
PERT may utilize three ‘time estimates’.
4
PERT was developed between 1950-60.