BANK Rajasthan Cooperative Board Clerk / Junior Assistant Mock Test 2021 Quantitative Aptitude Time and Work Work Efficiency
Akash is twice efficient as Bikram and Chetan take twice as much time as Bikram takes. Bikram completes the work in 8 days. Find the number of days taken by Akash and Chetan together to complete the work.
1
16 days
2
(16/5) days
3
(16/3) days
4
(16/7) days
5
(15/6) days