Comprehension Passage

Direction: The below pie chart shows the percentage of total work done by 6 persons viz. A, B, C, D, E, and F and the table given below shows the time taken by these persons to complete that percentage of work.

Person

A

B

C

D

E

F

Number of Days in which the percentage of work done

6

8

2.5

3

6

9

 

Now answer the following questions based on the above pie chart and table:

B started the work and left after working for 5 days. A, C, and D joined the work and A left the work 6 days before the completion while C and D work for the whole time. Find the time for which A worked.

1
\(10\frac{{10}}{{71}}\;days\)
2
\(9\frac{2}{{71}}\;days\)
3
\(11\frac{2}{{71}}\;days\)
4
\(3\frac{{10}}{{71}}\;days\)
5
\(3\frac{{51}}{{71}}\;days\)