A contractor employed ‘P’ number of people in order to finish the work in 4 days. But due to some reason, everyday exactly 5 people didn’t come to work. As a result the whole work was completed in 3/4th more time than usual. Find the value of ‘P’.
1
50
2
40
3
35
4
25
5
20