Sahil, Nikhil and Akhil can complete a work in 10 days. Sahil alone take 20 days to complete a work while Nikhill takes 5 more days than Sahil to finish the work. They were paid Rs 60,000 for it. What is the share of Akhil in the earnings?
1
Rs. 8000
2
Rs. 5000
3
Rs. 7500
4
Rs. 9000
5
Rs. 6000