Comprehension Passage

Direction: In the following table, the wages for different category of workers for different six projects are given. Study the table given and answer the question.

Note: Some data in the table is missing.

(Wages, in Rs. per day, for different category of workers for different projects)

Workers

Projects

P

Q

R

S

T

U

Skilled

750

775

625

500

-

450

Semi-Skilled

625

-

525

475

625

425

Unskilled

550

650

-

x

575

(x - 25)

The overall estimate of Project P is Rs. 22, 600 and the number of skilled, semi-skilled and unskilled people is 2 : 4 : 3. The overall estimate of Project Q is Rs. 17,750 and the number of skilled, semi-skilled and unskilled people is 2 : 1 : 2. If the number of skilled people working in project P is 20% less than the number of skilled people working in project Q, then, find the total wages of semi-skilled people working in Project Q?

1
Rs. 3500
2
Rs. 3000
3
Rs. 4000
4
Rs. 4200
5
None of these