A is able to complete 75% of the work in x days, while B can finish the task in (x + 12) days, and C requires 2x days to complete the work individually. When A, B, and C collaborate, they are able to finish the entire job in 9(27/37) days. Can you identify the numerical value of x?

1
12
2
18
3
20
4
24
5
15