Comprehension Passage

Directions: The data below represents the number of people required for various project to be completed in different number of days. Use this information to answer the question asked.

Project

Situation I

Situation II

Number of Workers

Days Required

Number of Workers

Days Required

P1

x

(x + 5)

(x – 5)

(x + 15)

P2

y

(y + 10)

40

(y – 5)

P3

50

z

80

(y – 10)

P4

y

(z + 9)

(x + 16.25)

z

In a group A, if the total number of workers is (0.2x × 0.8y), then, what is the number of days required by group A to complete Project P2? (If y > 15)

1
15 days
2
20 days
3
10 days
4
12.5 days
5
25 days

Sponsored

hivanix.in

Visit

This quiz is brought to you by hivanix.in

🌐 Web App Development

Quick Navigation