Comprehension Passage
Directions: The data below represents the number of people required for various project to be completed in different number of days. Use this information to answer the question asked.
|
Project |
Situation I |
Situation II |
||
|
Number of Workers |
Days Required |
Number of Workers |
Days Required |
|
|
P1 |
x |
(x + 5) |
(x – 5) |
(x + 15) |
|
P2 |
y |
(y + 10) |
40 |
(y – 5) |
|
P3 |
50 |
z |
80 |
(y – 10) |
|
P4 |
y |
(z + 9) |
(x + 16.25) |
z |
In a group A, if the total number of workers is (0.2x × 0.8y), then, what is the number of days required by group A to complete Project P2? (If y > 15)
1
15 days
2
20 days
3
10 days
4
12.5 days
5
25 days